Be Ready for DOB Audits: New TR8 Progress Inspection Guidelines

By AMAA
25 June 2025 | 10 min read

AMAA is committed to keeping you informed about critical NYC building compliance updates. The DOB has issued Buildings Bulletin 2025-003, which outlines new documentation and reporting standards for projects selected for audit—specifically related to TR8 Progress Inspections and energy code compliance.   

What to know about TR8 Progress Inspections

New Submission Milestones

For projects that come under audit, Progress Inspection Reports may need to be submitted at three specific phases of construction:

  • Before enclosure of the thermal envelope (e.g., EIFS, cladding, brick veneer).
  • After rough-in and sealing, but prior to installing interior finishes. 
  • Upon completion of mechanical and lighting systems, before painting and final finishes.          

Required Documentation

Each inspection report should include: 

  • Date, time, and type of inspection.
  • Description of the observed assembly, system, or test.
  • Specific drawing reference verified during inspection.
  • Date-stamped photos of each inspected condition.

Submission Format

Reports must be emailed to TR8inspections@buildings.nyc.gov at the designated stages. These reports support final energy code compliance sign-off.

Stay Compliant

While not required for every project, missing or incomplete documentation during an audit may result in Stop Work Orders or other enforcement actions. AMAA can help ensure you're prepared—reach out today to stay ahead of compliance issues.

For more information about TR8 Inspection Updates, see the: FULL BULLETIN